EU GMP Annex 1 9.38

9. Environmental & process monitoring › Aseptic process simulation (APS) (also known as media fill)

Section text

APS should be performed as part of the initial validation, with at least three consecutive satisfactory simulation tests that cover all working shifts that the aseptic process may occur in, and after any significant modification to operational practices, facilities, services or equipment which are assessed to have an impact on the sterility assurance of the product (e.g. modification to the HVAC system, equipment, changes to process, number of shifts and numbers of personnel, major facility shut down). Normally, APS (periodic revalidation) should be repeated twice a year (approximately every six months) for each aseptic process, each filling line and each shift. Each operator should participate in at least one successful APS annually. Consideration should be given to performing an APS after the last batch prior to shut down, before long periods of inactivity or before decommissioning or relocation of a line.

Source: European Commission, DG SANTE · © European Union. Reuse is authorised provided the source is acknowledged (Commission Decision 2011/833/EU on the reuse of Commission documents). · retrieved 2026-11-15

Weekly Newsletter

Get new findings like these every Monday

Every Monday we email the week's new findings and actions from the FDA, EMA, Health Canada and MFDS. Each one links to its record on our site, where you'll find the regulator's original document. We'll also let you know when the site gains new features. Unsubscribe any time with one click.

See recent findings first

Sent every Monday · a confirmation email follows when you subscribe · unsubscribe from the footer of any email.