Skip to content

ICH

ICH Q9(R1) 4.3

Risk Assessment

4. GENERAL QUALITY RISK MANAGEMENT PROCESS

Section text

Risk assessment consists of the identification of hazards and the analysis and evaluation of risks associated with exposure to those hazards (as defined below). Quality risk assessments begin with a well-defined problem description or risk question. When the risk in question is well defined, an appropriate risk management tool (see examples in section 5) and the types of information needed to address the risk question will be more readily identifiable. As an aid to clearly defining the risk(s) for risk assessment purposes, three fundamental questions are often helpful:

1. What might go wrong?

2. What is the likelihood (probability) it will go wrong?

3. What are the consequences (severity)?

Hazard identification is a systematic use of information to identify hazards referring to the risk question or problem description. Information can include historical data, theoretical analysis, informed opinions, and the concerns of stakeholders. Hazard identification addresses the “What might go wrong?” question, including identifying the possible consequences. This provides the basis for further steps in the quality risk management process.

Risk analysis is the estimation of the risk associated with the identified hazards. It is the qualitative or quantitative process of linking the likelihood of occurrence and severity of harms. In some risk management tools, the ability to detect the harm (detectability) also factors in the estimation of risk.

Risk evaluation compares the identified and analyzed risk against given risk criteria. Risk evaluations consider the strength of evidence for all three of the fundamental questions. In doing an effective risk assessment, the robustness of the data set is important because it determines the quality of the output. Revealing assumptions and reasonable sources of uncertainty will enhance confidence in this output and/or help identify its limitations.

Uncertainty is due to a combination of incomplete knowledge about a process and its expected or unexpected variability. Typical sources of uncertainty include gaps in knowledge, gaps in pharmaceutical science and process understanding, sources of harm (e.g., failure modes of a process, sources of variability), and probability of detection of problems.

The output of a risk assessment is either a quantitative estimate of risk or a qualitative description of a range of risk. When risk is expressed quantitatively, a numerical probability is used. Alternatively, risk can be expressed using qualitative descriptors, such as “high”, “medium”, or “low”, which should be defined in as much detail as possible. Sometimes a "risk score" is used to further define descriptors in risk ranking. In quantitative risk assessments, a risk estimate provides the likelihood of a specific consequence, given a set of risk-generating circumstances. Thus, quantitative risk estimation is useful for one particular consequence at a time. Alternatively, some risk management tools use a relative risk measure to combine multiple levels of severity and probability into an overall estimate of relative risk. The intermediate steps within a scoring process can sometimes employ quantitative risk estimation.

Glossary terms that cite this clause

Source: International Council for Harmonisation (ICH) · © ICH. Per the legal notice in each guideline, the document may be used, reproduced and distributed provided ICH's copyright is acknowledged; any adaptation or translation must be labelled as such and must not imply ICH endorsement. · retrieved 2026-11-15

Weekly Newsletter

Get new findings like these every Monday

Every Monday we email the week's new findings and actions from the FDA, EMA, Health Canada and MFDS. Each one links to its record on our site, where you'll find the regulator's original document. We'll also let you know when the site gains new features. Unsubscribe any time with one click.

See recent findings first

Sent every Monday · a confirmation email follows when you subscribe · unsubscribe from the footer of any email.