ICH Q7 12.30

12. VALIDATION

Section text

Before starting process validation activities, appropriate qualification of critical equipment and ancillary systems should be completed. Qualification is usually carried out by conducting the following activities, individually or combined:

- Design Qualification (DQ): documented verification that the proposed design of the facilities, equipment, or systems is suitable for the intended purpose.

- Installation Qualification (IQ): documented verification that the equipment or systems, as installed or modified, comply with the approved design, the manufacturer’s recommendations and/or user requirements.

- Operational Qualification (OQ): documented verification that the equipment or systems, as installed or modified, perform as intended throughout the anticipated operating ranges.

- Performance Qualification (PQ): documented verification that the equipment and ancillary systems, as connected together, can perform effectively and reproducibly based on the approved process method and specifications.

Glossary terms that cite this clause

Source: International Council for Harmonisation (ICH) · © ICH. Per the legal notice in each guideline, the document may be used, reproduced and distributed provided ICH's copyright is acknowledged; any adaptation or translation must be labelled as such and must not imply ICH endorsement. · retrieved 2026-11-15

Weekly Newsletter

Get new findings like these every Monday

Every Monday we email the week's new findings and actions from the FDA, EMA, Health Canada and MFDS. Each one links to its record on our site, where you'll find the regulator's original document. We'll also let you know when the site gains new features. Unsubscribe any time with one click.

See recent findings first

Sent every Monday · a confirmation email follows when you subscribe · unsubscribe from the footer of any email.