12. VALIDATION
조항 원문
Before starting process validation activities, appropriate qualification of critical equipment and ancillary systems should be completed. Qualification is usually carried out by conducting the following activities, individually or combined:
- Design Qualification (DQ): documented verification that the proposed design of the facilities, equipment, or systems is suitable for the intended purpose.
- Installation Qualification (IQ): documented verification that the equipment or systems, as installed or modified, comply with the approved design, the manufacturer’s recommendations and/or user requirements.
- Operational Qualification (OQ): documented verification that the equipment or systems, as installed or modified, perform as intended throughout the anticipated operating ranges.
- Performance Qualification (PQ): documented verification that the equipment and ancillary systems, as connected together, can perform effectively and reproducibly based on the approved process method and specifications.
본문은 원문(영어)입니다. 국문 번역은 준비 중입니다.
이 조항을 근거로 든 용어
출처: International Council for Harmonisation (ICH) · © ICH. Per the legal notice in each guideline, the document may be used, reproduced and distributed provided ICH's copyright is acknowledged; any adaptation or translation must be labelled as such and must not imply ICH endorsement. · 수집일 2026-11-15